The spring season has been full of activity this year but nothing can stop Stellar Construction from diligently working on the HSI expansion. Over the last 60 days the new building has been going up piece by piece, the parking lot installed with aprons and the Exterior Insulation Finishing System (EIFS) is in the process of being applied.

Mark Carmouche with Stellar Construction expects to complete the exterior next week.  The projects to be completed are finishing the exteriors of the new addition and the existing building with EIFS, painting both buildings, painting the parking lot stripes, installing curbs, opening up and installing two interior doors from the current building to the new building, the final grading and laying sod.

“Once the permit has been approved we can start working on the interior of the building,” said Mark Boozer, president of Hydronic Systems.  “Everyday we see more and more accomplished and are excited to showcase our new space that will help us better serve our customers.”

To learn more about Stellar Construction CLICK HERE.